F-13(OPM) Revised Syllabus |
|||
Time Allowed : 3 Hours | Full Marks : 100 | ||
The figures in the margin on the right side indicate full marks | |||
Answer Question No. 1 & Question No. 7, which are compulsory and any two other questions from Section I and any two other from Section II. | |||
Please answer all the bits of a question at one place. | |||
Section I | |||
Marks |
1. | (a) | Match each item in the left hand Column-1 with an appropriate item in the right hand column-II:
|
1x5 | ||||||||||||||||||||||||||||||
(b) | Explain the following acronyms:
|
1x5 | |||||||||||||||||||||||||||||||
(c) | In each of the cases given below one out of four answers is correct. Indicate the correct answer and give your workings/reasons briefly:
|
2x3 | |||||||||||||||||||||||||||||||
(d) | Distinguish between (only two points each):
|
2x2 | |||||||||||||||||||||||||||||||
2. | (a) | Mention the factors that are normally covered in the choice of Appropriate Technology. | 4 | ||||||||||||||||||||||||||||||
(b) | Smith Engineering Ltd. (SEL) produced one type of mild steel pins for supply to a pump manufacturer. The pins have a miameter of 1 cm and length of 5 cms. The pins are manufactured in lathes by turning and facing from mild steel forged and annealed rods supplied by two firms A and B who supplies the material in following shape and size:
|
11 |
Please turn over |
( 2 )
F-13(OPM) Revised syllabus |
Marks |
The company (SEL) can do annealing of the forged rods supplied by Firm B in its own heat treatment shop at a cost of Rs. 10.00 per rod on an average. Weight of mild steel is 7.8 gms per cubic centimeter and machining cost for forged and annealed mild steel is Rs. 300.00 per kg. of metal removal. Asuming that scrap value of chips is negligible. As a Cost Accountant which firm will you choose? | |||||||||||||||||||||||||||
3. | (a) | A factory has three departments X, Y and Z to manufacture two products A and B. Department 'X' can produce parts for 7000 units of A or parts for 12000 units of B per week, but cannot do both at the same time though parts for some A and for some B can be produced. Similarly Department 'Y' can produce 9000 parts for A or 6000 parts for B or combinations in between.
Final assembly is undertaken in department 'Z' with separate assembly lines for A and B with maximum capacities by 6000 and 4000 units respectively. Both lines can be operated at the same time. What is the Optimal Product Mix? |
7 | ||||||||||||||||||||||||
(b) | A radial bearing manufacturing units produces three types of bearing namely X, Y and Z during the year 2006-2007, the unit manufactured 20000; 10000 and 13650 Nos. of X, Y and Z respectively. The standard Man-hours (SMH) of X, Y and Z are 12, 14 and 16 respectively. The unit worked for 8 hours per day for single shift for Monday to Friday and 4 hours shift on saturday. There were 50 working weeks during the year. The ratio of piece workers to Day workers among Industrial employees was 1:0.4 and total No. of Industrial employees was 560. Assuming on an average 15% absenteeism among Industrial employees, what was the productivity of piece workers during the year 2006-2007? | 8 | |||||||||||||||||||||||||
4. | (a) | What are the objectives of using Control Charts for Variables? | 4 | ||||||||||||||||||||||||
(b) | 20 samples were obtained from the fabric being produced by a weaving machine. The number of defects per 100 metres of cloth for the samples is given below:
|
4+7 | |||||||||||||||||||||||||
5. | (a) | Detail the steps involved in making a work sampling study | 6 | ||||||||||||||||||||||||
(b) | HIPROD CO LTD manufactures three different items of tools. The time required to produce each tool on different operations is as follows:
The workers are trained in each trade as such their services are not inter-changeable. they are paid at Rs. 11.00 per hour. The workers are paid for 2500 hours per annum which includes 200 hours for leave in which time substitute operators are appointed and for 300 hours the machines are taken for overhaul. Using the above data calculate:
|
2+5+2 |
Please turn over |
( 3 )
F-13(OPM) Revised syllabus | Marks |
6. | Write short notes on the following:
|
4+4+4+3 | |||||||||||||||||||||||||
Section II | |||||||||||||||||||||||||||
7. | (a) | Expand the following acronyms:
|
1x5 | ||||||||||||||||||||||||
(b) | Fill up the blanks in the following sentences:
|
1x5 | |||||||||||||||||||||||||
(c) | Mention whether the following statements are True or False:
|
1x5 | |||||||||||||||||||||||||
(d) | Match the statement in Column-I with the statement under Column-II:
|
1x5 |
Please turn over |
( 4 )
F-13(OPM) Revised syllabus |
Marks |
8. | (a) | A manufacturer is considering four locations for establishing a new project. The location specific costs are as follows:
If cost of capital is 10%, determine the most suitable location for volumes of 50,000 units, 1 lakh units and 1.5 lakh units. |
9 | |||||||||||||||||||||
(b) | What are the skills and attributes required of a successful Project Manager? | 6 | ||||||||||||||||||||||
9. | (a) | Xenith Co. has been offered a contract to build and deliver nine extruding presses to the ABC Bottling Co. The contract price negotiated is contingent on meeting a specified delivery time, a bonus being given for early delivery. The marketing department has established the following cost and time information.
The normal delivery time is 16 weeks for a contract price of Rs. 1,40,000. Based on the claculated profitability for each of the following specified delivery time, what delivery schedule do you recommend that Zenith Co. may implement?
(Note: a=to: optimistic time b=tp: pessimistic time m=tm: most likely time.) |
10+2 | |||||||||||||||||||||
(b) | What is option clause in a Contract? When it is included in a Contract? | 2+1 |
Please turn over |
( 5 )
F-13(OPM) Revised syllabus | Marks |
10. | (a) | What information would be required for preparing the Projected Balance Sheet of a Company? | 3 | |||||||||||||||||||||
(b) | The Balance Sheet of M/s. OPTIMA LIMITED on 31st March 2997 is given below:
The projected Income Statement and the distribution of earnings for the year 2007-08 are as follows:
An additional outlay of Rs. 30 lakhs is planned for fixed assets in the year 2007-08, which is proposed to be financed by Rs. 20 lakhs of Secured and Rs. 10 lakhs of Unsecured Loans. Further, Secured Loans of Rs. 5 lakhs are also proposed to be discharged. The operations in 2007-08 are expected to increase the stocks by Rs. 10 lakhs and the credit sales by Rs. 15 lakhs. Based on the information given supra you are required to prepare the Projected Cash Flow Statement for the year 2007-08 and the Projected Balance Sheet as on 31st March 2008. |
6+6 | ||||||||||||||||||||||
11. | (a) | A consultant is appointed for a paper project for undertaking certain assignments at a total fee at Rs. 530 lakhs. Terms of payment include 10% advance on the fee and a 5% retention on the progress payments. At a certain point in time, he achieved the following milestones progress against each head of deliverables. What is the overall progress achieved by the consultant and the consulting fee earned by him? What is the amount payable on him at the point of time?
|
7 | |||||||||||||||||||||
(b) | A transporter finds from his past records that the costs per year of maintaining a car whose purchase price is Rs. 1,60,000 are as given below:
At what age he should replace a Car? |
8 | ||||||||||||||||||||||
12. | Write short notes on the following:
|
4+4+4+3 | ||||||||||||||||||||||
__________ |
Disclaimer ♣ Privacy Policy ♣ Terms of Service ♣ Who We Are
© Krishbhavara ♣