7. | (a) | Expand the following acronyms: | 1x5 | |
| | (i) | MTBF | | (0) |
| | (ii) | IIBI | | (0) |
| | (iii) | FDI | | (0) |
| | (iv) | BOOT | | (0) |
| | (v) | LRC | | (0) |
| (b) | Fill up the blanks in the following sentences: | 1x5 | |
| | (i) | Total float of an ________ is the amount of time an activity of a Project can be delayed without affecting the overall ________ of the Project. | | (0) |
| | (ii) | Benefit Cost Ratio is the ratio of ________ Value of Benefits to Present ________ of Investments. | | (0) |
| | (iii) | Head Slack is the difference between the ________ and the ________ Occurrence Times of the Head Event of an Activity. | | (0) |
| | (iv) | Capital Ratio is the ________ of ________ Ratio. | | (0) |
| | (v) | Detailed ________ Report is prepared ________ the Feasibility Report. | | (0) |
| (c) | Mention whether the following statements are True or False: | 1x5 | |
| | (i) | Social analysis deals with impact of investment in Project on people and their lives. | | (0) |
| | (ii) | Task Force Organisation Structure is created by sharing authority between the Project Manager and the Functional Manager. | | (0) |
| | (iii) | In term Rate Contract, the Contractor is paid in lumpsum at the end of the Contract. | | (0) |
| | (iv) | IRR is the discount rate at which the Present Value of future cost inflows equal the Present Value of Project cash outflows/investment. | | (0) |
| | (v) | Sensitivity Analysis is about estimating the impact of market fluctuations on project profitability. | | (0) |
| (d) | Match the statement in Column-I with the statement under Column-II: Column I | Column II | (i) | Balancing Project | (A) | Enable to continue in Business and compete effectively | (ii) | Modernization Project | (B) | Are undertaken to maintain Production, at acceptable efficiency level | (iii) | Expansion project | (C) | Seeks profitable investment opportunities, in altogether new areas | (iv) | Diversification Project | (D) | Minimize under–utilization of capacity | (v) | Replacement Project | (E) | Enables enlargement of plant capacity | | 1x5 | (0) |
8. | (a) | A manufacturer is considering four locations for establishing a new project. The location specific costs are as follows: (Costs in rupees) | Item | I | II | III | IV | 1. Plant & Machinery 2. Taxes per Year 3. Electricity per Year 4. Water per Year 5. Labour per Unit 6. Materials & Equipment per Unit 7. Transportation per Unit | 6,00,000 30,000 35,000 8,000 1.00 0.50 0.05 | 5,00,000 28,000 30,000 7,000 1.50 0.60 0.10 | 5,50,000 65,000 28,000 7,000 1.10 0.40 0.10 | 5,00,000 45,000 25,000 6,000 1.75 0.55 0.05 |
If cost of capital is 10%, determine the most suitable location for volumes of 50,000 units, 1 lakh units and 1.5 lakh units. | 9 | (0) |
| (b) | What are the skills and attributes required of a successful Project Manager? | 6 | (0) |
9. | (a) | Xenith Co. has been offered a contract to build and deliver nine extruding presses to the ABC Bottling Co. The contract price negotiated is contingent on meeting a specified delivery time, a bonus being given for early delivery. The marketing department has established the following cost and time information. Activity | Normal Time (Weeks) | Normal Cost Rs. | Crash Time (Weeks) | Crash Cost Rs. | a | b | m | 1 — 2 2 — 3 2 — 4 2 — 5 3 — 6 4 — 6 5 — 7 6 — 7 | 1 1 1 5 2 5 4 1 | 5 7 5 11 6 7 6 5 | 3 4 3 8 4 6 5 3 | 15,000 18,000 14,000 15,000 13,000 12,000 20,000 17,000 | 1 3 2 7 2 4 4 1 | 19,000 24,000 16,000 16,000 15,000 13,600 24,000 20,600 |
The normal delivery time is 16 weeks for a contract price of Rs. 1,40,000. Based on the calculated profitability for each of the following specified delivery time, what delivery schedule do you recommend that Zenith Co. may implement? Contract delivery time (Weeks) | Contract Amount (Rs.) | 15 14 13 12 | 1,42,500 1,45,000 1,50,000 1,52,000 |
(Note: a=to: optimistic time b=tp: pessimistic time m=tm: most likely time.) | 10+2 | (0) |
| (b) | What is option clause in a Contract? When it is included in a Contract? | 2+1 | (0) |
10. | (a) | What information would be required for preparing the Projected Balance Sheet of a Company? | 3 | (0) |
| (b) | The Balance Sheet of M/s. OPTIMA LIMITED on 31st March 2007 is given below: (Rs. in lakhs) | Liabilities | Assets | Share Capital Reserves & Surplus Secured Loans Unsecured Loans Current Liabilities Provisions | 100 20 80 50 90 20 | Fixed Assets Investments Current Assets Cash Receivables Inventories |
20 80 80 | 180 —
180 | 360 | 360 |
The projected Income Statement and the distribution of earnings for the year 2007–08 are as follows: (Rs. in lakhs) | Sales Cost of Goods sold Depreciation Earnings Before Interest & Tax (EBIT) Interest Profit Before Interest & Tax (PBT) Tax @50% Profit After Tax (PAT) | 400 300 20 80 20 60 30 30 | Dividends Retained Earnings | 10 20 |
An additional outlay of Rs. 30 lakhs is planned for fixed assets in the year 2007–08, which is proposed to be financed by Rs. 20 lakhs of Secured and Rs. 10 lakhs of Unsecured Loans. Further, Secured Loans of Rs. 5 lakhs are also proposed to be discharged. The operations in 2007–08 are expected to increase the stocks by Rs. 10 lakhs and the credit sales by Rs. 15 lakhs. Based on the information given supra you are required to prepare the Projected Cash Flow Statement for the year 2007-08 and the Projected Balance Sheet as on 31st March 2008. | 6+6 | (0) |
11. | (a) | A consultant is appointed for a paper project for undertaking certain assignments at a total fee at Rs. 530 lakhs. Terms of payment include 10% advance on the fee and a 5% retention on the progress payments. At a certain point in time, he achieved the following milestones progress against each head of deliverables. What is the overall progress achieved by the consultant and the consulting fee earned by him? What is the amount payable on him at the point of time? SI.No | Assignment deliverables | Total Quantity (Nos.) | Total Work Value (Rs. in lakhs) | Progress Achieved (%) | 1. 2. 3. 4. 5. 6 | Specifications & Tendering Documents Tender Evaluation Work Order Preparation Detailed Design & Drawings Review of Vendors' Drawings Preparations of As Built Drawings | 30 30 30 1200 540 600 | 120 60 30 210 90 20 | 30 20 15 10 5 0 | | 7 | (0) |
| (b) | A transporter finds from his past records that the costs per year of maintaining a car whose purchase price is Rs. 1,60,000 are as given below: Year | Maintenance Costs (in Rs.) | Resale Price (in Rs.) | 1 2 3 4 5 6 7 8 | 8,000 9,000 10,500 13,000 15,000 20,000 25,000 30,000 | 1,45,000 1,32,000 1,22,000 1,14,000 1,09,000 90,000 70,000 50,000 |
At what age he should replace a Car? | 8 | (0) |
12. | Write short notes on the following: | 4+4+4+3 | |
| (a) | Venture Capital Funding of Projects; | | (0) |
| (b) | "Invisible Walls" in Project Cost Estimation; | | (0) |
| (c) | Zero Based Budgeting (ZBB); | | (0) |
| (d) | Consortium Lending. | | (0) |