| 3. |
The following cost information for a period is available for a small engineering unit: |
16 |
|
(a) |
Allocated expenditure.
| Allocated |
| | | Production Departments | Service Departments |
| | Total (Rs.) | Machine shop | Assembly | General Plant Services | Stores & Misc. |
| Indirect wages | 29,300 | 8,000 | 6,000 | 4,000 | 11,300 |
| Stores consumed | 6,700 | 2,200 | 1,700 | 1,100 | 1,700 |
| Supervisory Salaries | 14,000 | — | — | 14,000 | — |
| Other Salaries | 10,000 | — | — | 10,000 | — |
| |
|
(b) |
Expenditure to be apportioned
Power and Fuel Rent Insurance Depreciation |
15,000 15,000 3,000 1,00,000 |
|
|
|
(c) |
Expenditure to be apportioned
| | Floor Area (Sq. ft) | H.P. hrs. — | No. of Employees | Investment (Rs.) |
Machine Shop Assembly General Plant Stores and Maintenance |
2,000 1,000 500 1,500 |
3,500 500 — 1,000 |
30 15 5 10 |
6,40,000 2,00,000 10,000 1,50,000 |
|
|
|
(d) |
Basis of distribution of service dept. costs:
Stores and Maintenance |
Machine Shop 50% |
Assembly
20% |
General Plant Services 30% |
Stores & Misc. — |
| General Plant and Services In proportion to the number of employees. | |
|
|
|
You are required to prepare an overhead distribution statement in detail. Service department costs are to be distributed by continued distribution. Carry through three cycles. Calculations to be shown to the nearest rupee. |
|
| 4 |
Production in a manufacturing company passes through three distinct processes I, II and III. The output of each process is transferred to the next process and the output of process III is transferred to finished goods stock. The normal wastage in each process and the realisable value of the same are given below:
| Process | % of normal waste related to input | Realisable value per Unit |
I II III | 5 7 10 | Re. 0.70 Re. 0.80 Re. 1.00 |
|
16 |
| |
| The details of cost data and output for a month are as follows: |
| Process |
| I | II | III |
Material Consumed Direct Labour Cost Production Expenses Output |
(Rs.) (Rs.) (Rs.) (Units) |
1,20,000 80,000 40,000 38,000 |
40,000 60,000 40,000 34,600 |
40,000 60,000 28,000 32,000 |
|
|
|
Process I was fed wutg 40,000 units of input costing Rs. 3,20,000. There were no opening of closing work progress.
Prepare the process accounts for the month. |
|
( 3 )
I-5(CMA) Revised syllabus |
Marks |
| 5. |
(a) |
What are the important applications of marginal costing as a tool for decision making? |
4 |
|
(b) |
A company manufactures and sellts two standards products X and Y using the same raw material, labour and identical machines. Further particulars are given below:
| X | | Y |
| Perunit | |
Direct Material @ Rs. 20/kg Direct Labour @ Rs. 15/hr. Variable Overheads Machine hours required Fixed Overheads (allocated) |
Rs. Rs. Rs.
Rs. |
20 15 15 ½ hr |
|
Rs. Rs. Rs.
Rs. |
30 15 15 3/4 hr 18 |
| Per annum | |
Maximum Demand (units) Current Production (units) | | 18,000 15,000 | | 15,000 12,000 |
|
12 |
|
|
Labour and materials are available according to requirements. But machine capacity cannot be increased immediately and the available capacity has been fully utilised by the current production plan.
Required
| (i) | Current contribution analysis. |
| (ii) | Profit currently earned by the company. |
| (iii) | Alternative production plan, if any, more profitable to the company. |
| (iv) | Profit expected to be earned under the suggested plan. |
|
|
| 6. |
(a) |
What is meant by 'flexible budgeting'? Mention some important uses of this technique. |
4 |
|
(b) |
A newly established manufacturing company has an installed capacity to produce 1,00,000 units of a consumer product annually. However its practical capacity is only 90%. The actual capacity utilisation may be substantially lower, as the firm is new to the market and demand is uncertain. The following budget has been prepared for 90% capacity utilisation: |
12 |
| |
Direct Materials Direct Labour Direct Expenses Production Overhads Administration Overheads Selling and Distribution |
Cost per unit Rs. 12 8 5 10 5 6 |
(40% variable) (100% fixed) (50% variable) |
| |
|
You are required to prepare budgets at 60%, 70% and 80% levels of capacity utilisation giving clearly the unit variable cost, the unit fixed cost and the total costs under various heads at all the above levels. |
|
| 7. |
(a) |
What is 'Fixed Production Overhead Variance'? Explain how this is calculated and further analysed. |
6 |
|
(b) |
Kolkata Furnitures manufactures modular tables, chairs and office desks. The standard labour times required per unit of table, chair and desk are 4 hours, 2 hours and 8 hours respectively. The budgeted production per week is 140 standard hours and budgeted fixed overheads per week is Rs. 70,000.
During a particular week the firm achieved the following output:
Tables Chairs Desks |
8 Nos. 8 Nos. 9 Nos. |
|
10 |
|
|
The actual fixed production overhead amounted to Rs. 75,000.
Calculate:
| (i) | Fixed Production Overhead total variance; |
| (ii) | Fixed Production Overhead expenditure variance; |
| (iii) | Fixed Production Overhead volume variance. |
|
|
| 8. |
Write short notes on any four of the following:
| (a) | Management by exception; |
| (b) | Break even analysis; |
| (c) | Integrated accounts; |
| (d) | Equivalent production; |
| (e) | Liquidity ratios. |
|
4x4=16 |
__________ |
ca,icwa,cwa,cs,exam,previous,past,question,papers,suggested,guideline,answers
Disclaimer ♣ Privacy Policy ♣ Terms of Service ♣ Who We Are
♣ Copyright © Krishbhavara. All rights reserved
♣ Site optimized for Internet Explorer 5.5 and above