6. | (a) | Match each item in Column I with the most suitable description in Column II: Column I | Column II | (A) (B) (C) (D) (E) | Project Viability Checking Short Term Financing for working Capital Utility Capital Ratio Resource Allocation | (i) (ii) (iii) (iv) (v) | Power Investment & Turnover Cost Benefit Analysis Project Activity Commercial Paper | | 1x5 | (0) |
| (b) | Expand the following acronyms: (i) | FDI, | (ii) | BEP, | (iii) | LRC, | (iv) | LOB, | (v) | ACWP. | | 1x5 | (0) |
| (c) | In each of the cases given below one out of our answer is correct. Indicate the correct answer: | 1x5 | |
| | (i) | If an activity of a critical path in a network diagram has a pessimistic time of 18 days and a standard deviation of 4, the optimistic time estimate for the activity is A. | 4 days | B. | 6 days | C. | 8 days | D. | 12 days | | | (0) |
| | (ii) | Variation in the Cost of capital changes the ranking of a project as per which of the following appraisal methods. A. | NPV | B. | BCR | C. | P 1 | D. | All of the above | | | (0) |
| | (iii) | The Detail Project Report (DPR) is generally prepared for submission to the A. | Financial Institutions | B. | Management | C. | Board of Directors | D. | None of the above | | | (0) |
| | (iv) | Which of the following statement(s) is/are true? A. | Total float is a sum of free float and independent float | B. | Free float is always for all activities on the critical path | C. | Independent float can be negative or positive | D. | Only the activities on the critical path have an independent float of zero. | | | (0) |
| | (v) | In matrix form of project organization, A. | The hierarchical principle is ignored | B. | Responsibility and authority are commensurate | C. | There is dual subordination | D. | Both (A) and (C) above. | | | (0) |
| (d) | Find out whether the following statements are ‘True’ or ‘False’ : | 1x5 | |
| | (i) | In Item rate contracts, the Contractor is paid a lumpsum amount at the end of the Contract. | | (0) |
| | (ii) | Normal Costs are estimates of Direct Costs of a Project to be executed in Normal Time. | | (0) |
| | (iii) | Royalty is the consideration paid to the Collaborator annually for transfer of technical know–how over the duration of the agreement. | | (0) |
| | (iv) | Head Slack is the difference between the Earliest and the Latest Occurrence times of the Tail event of an Activity. | | (0) |
| | (v) | Benefit Cost Ratio is the ratio of Present Value of Benefits to the Present Value of Investments. | | (0) |
7. | (a) | What is Social Cost–Benefit analysis? What are the main differences between Social Cost Benefit analysis and the Commercial Calculations in Project Appraisal? | 1+4 | (0) |
| (b) | The top management of ZAVRI LTD. is considering the problem of marketing a new product. The investment required in the project is Rs.15,000. The three factors that are uncertain are the selling price, variable cost and the annual sales volume. The product has a life of only one year. The management has collected the following data regarding the possible levels of these three factors: Unit Selling Price (Rs.) | Probability | Unit variable Cost (Rs.) | Probability | Sales Volume Units | Probability | 14 15 16 | 0.35 0.50 0.15 | 2 3 4 | 0.30 0.50 0.20 | 3,000 4,000 5,000 | 0.25 0.40 0.35 |
Consider the following three series of random Numbers: Series 1: 82, 84, 28, 82, 36, 92, 73, 91, 63, 29 Series 2: 27, 26, 92, 63, 83, 03, 10, 39, 10, 10 Series 3: 23, 57, 99, 84, 51, 29, 41, 11, 66, 30 |
Required: Using Monte Carlo simulation technique, determine the expected profit for the above project on the basis of 10 trails. | 2+6+2 | (0) |
8. | (a) | What is Gestation period of a project? How the financing decisions are Governed by the gestation period of the project? | 1+3 | (0) |
| (b) | PRECISION TOOLS LTD. has obtained a contract to built and deliver nine extruding presses to MARISON LTD. The contract price negotiated is contingent on meeting a specified delivery time, a bonus being given for early delivery. The marketing department has established the following cost and time information: Activity | Normal time (Weeks) | Crash time (Weeks) | Normal cost (Rs.) | Crash cost (Rs.) | 1–2 2–3 2–4 2–5 3–6 4–6 5–7 6–7 | 3 4 3 8 4 6 5 3 | 1 3 2 7 2 4 4 1 | 15,000 18,000 14,000 15,000 13,000 12,000 20,000 17,000 | 19,000 24,000 16,000 16,000 15,000 13,600 24,000 20,600 |
The normal delivery time is 16 weeks for a Contract Price of Rs.1,24,000. Required: Based on the calculated profitability for each of the following specified delivery time, what delivery schedule do you recommend that PRECISION TOOLS LTD. may implement? Contract delivery time (weeks) | Contract amount (Rs.) | 15 14 13 12 | 1,42,500 1,45,000 1,50,000 1,52,500 | | 2+1+2+5+1 | (0) |
9. | (a) | Explain Venture Capital Funding of Projects. | 5 | (0) |
| (b) | The Balance Sheet of VASTAN LTD. as on 31st March, 2009 is as follows: (Rs. in lakhs) Liabilities | | Assets | | | Share capital Reserves & Surplus Secured Loans Unsecured Loans Current Liabilities Provisions | 50 40 40 30 60 10 | Fixed Assets Investments Current Assets Cash Receivables Inventories |
10 40 65 | 110 5
115 | Total | 230 | | | 230 |
The projected Income Statement and distribution of earnings for the year 2009–10 are given below: (Rs.in lakhs) Cost of Goods Sold Depreciation Interest Tax Dividend Retained Earnings | 190 15 12 18 10 5 | Sales | 250 | Total | 250 | | 250 |
During the year 2009–10, the Company plans to raise secured loans of Rs.10 lakhs, repay a previous secured term loan to the extent of Rs.5 lakhs, acquire fixed assets worth Rs.15 lakhs and to raise its inventories by Rs.5 lakhs. During the year, Current Liabilities and Receivables are expected to increase by 5% each. Required: Prepare the Projected Cash Flow Statement for 2009–10 and the Projected Balance Sheet as on 31st March, 2010. | 5+5 | (0) |
10. | (a) | Explain “Life Cycle Costing” in Project Management. | 9 | (0) |
| (b) | The sales of a product during a 14 year period are as follows: Year | Sales | Year | Sales | 1 2 3 4 5 6 7 | 2,000 2,200 2,100 2,300 2,500 3,200 3,600 | 8 9 10 11 12 13 14 | 4,000 3,900 4,100 4,400 4,600 4,900 5,300 |
Required: Forecast the Sales for the 15th year, with the help of a trend line using Mid Point Method. | 6 | (0) |