This Paper has 28 answerable questions with 0 answered.
I—13(OPM) Revised Syllabus |
Time Allowed : 3 Hours | Full Marks : 100 |
Answer Question No. 1 which is compulsory and any two |
from Section I & any two questions from Section II |
Marks |
1. | (a) | What do the following abbreviations stand for? | 1x5 | |
| | (i) | AMT | | (0) |
| | (ii) | FMS | | (0) |
| | (iii) | VFM | | (0) |
| | (iv) | GT | | (0) |
| | (v) | CNC | | (0) |
| (b) | Match the words (a) to (j) under Column A with the corresponding words under Column B's (i) to (x) A | B | (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) | Jigs Annealing FSN Analysis Fixture Factor comparison Method Fork lift Trucks Bill of Materials Industrial Engineering Pay Back period Consumer's Risk | (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix) (x) | Inventory Control Material Handling Job Evaluation Quality Control Investment decision Tool Holding Method Study Production plan Work piece holding Heat treatment | | ½x10=5 | (0) |
| (c) | Match the Statement in Column A with the Statement under Column B: (A) | (B) | (i) | Balancing Project | (a) | Enable to continue in business and complete effectively. | (ii) | Moderisation Project | (b) | Are undertaken to maintain production at acceptable efficiency level. | (iii) | Expansion Project | (c) | Seeks profitable investment opportunities in altogether new area. | (iv) | Diversification Project | (d) | Minimise under utilisation of capacity | (v) | Replacement Project | (e) | Enables enlargement of the plant capacity. | | 1x5=5 | (0) |
| (d) | Define the following in not more than two sentences: | 1x5=5 | |
| | (i) | Benefit–Cost ratio; | | (0) |
| | (ii) | Conceptual Phase of Product–life cycle: | | (0) |
| | (iii) | Leasing financing; | | (0) |
| | (iv) | Item Rate Contract; | | (0) |
| | (v) | Event Slack. | | (0) |
2. | (a) | The Production Manager of a company is very much reluctant to initiate any action to improve productivity during the recession in his industry. Enumerate your views in the above context. | 6 | (0) |
| (b) | Dumpers are used to transport the Steel Ingot from the Melting shop to Ingot yard, which is situated at a distance of 0.6 km from the Melting shop. The capacity of the dumper is 8 tonnes. Due to speed restrictions, within the factory the dumper cannot run beyond 12 km/hour. In order to avoid congestion in the Melting shop, a minimum transportation of 3200 Tonnes is necessary per shift (of 8 hours duration). Find the number of dumpers that would be required. Ignore the loading and unloading time. | 8 | (0) |
| (c) | Name the important principles of Material Handling. | 6 | (0) |
3. | (a) | List the important points that are to be checked thoroughly for assessing the soundness of a plant layout. | 10 | (0) |
| (b) | Explain briefly the various types of maintenance undertaken in manufacturing operations. | 10 | (0) |
4. | (a) | Is “Wage Incentive Scheme” the only way for increasing labour productivity? Comment precisely. | 8 | (0) |
| (b) | Six jobs are to be carried out at three machines in the order: Lathe ? Milling ? Boring The data related to the time taken by each job on the 3 machines is given below. Each machine can process one job at a time. Time–Seconds | Job | Milling | Lathe | Boring | 1 2 3 4 5 6 | 300 400 200 100 400 300 | 500 800 900 700 600 750 | 400 800 700 600 200 450 |
You are required to– (i) | Determine the optimal sequence of the job. | (ii) | Ascertain the minimum elapsed time. | | 6+6 | (0) |
SECTION II |
Answer any two out of the following questions under Section II. |
5. | (a) | INTEL Project is having the following activities and their time estimates: Activity | Predecessor | Time (days) | | Optimistic (a) | Likely (m) | Pressimistic (b) | A B C D E F G H | – A A B C,B E D F,G | 2 8 14 4 6 6 18 8 | 4 12 16 10 12 8 18 14 | 6 16 30 16 18 22 30 32 | (i) Draw a PERT Network for the project. (ii) Identify the critical path and calculate the earliest expected time to complete the project. | 5+3+2 | (0) |
| (b) | What is 'pay back period'? Under what situations investment decisions are mainly guided by pay–back period method? | 2+2=4 | (0) |
| (c) | What are the main differences between PERT & CPM? | 6 | (0) |
6. | (a) | S Limited has Rs. 10,00,000 allocated for capital budgeting purposes. The following proposals and associated Profitability Index have been determined. Project | Amount (Rs.) | Profitability Index | 1 2 3 4 5 6 | 300,000 150,000 350,000 450,000 200,000 400,000 | 1.22 0.95 1.20 1.18 1.20 1.05 |
Which of the above investment should be undertaken? Assume that the Projects are indivisible and there is no alternative use of the money allotted for capital budgeting. | 10 | (0) |
| (b) | How gestation period of an on–going project affects Project financing decisions? | 2 | (0) |
| (c) | How to combat the dilemma of project failures especially due to the shortage of funds from the Government coffers. | 8 | (0) |
7. | (a) | An Investor wants to invest in a profitable project considering the opportunities available and business environment. As a Cost Accountant, suggest some sources for Project identification. | 10 | (0) |
| (b) | What is Feasibility Study? | 6 | (0) |
| (c) | What are the main objectives of pre–feasibility Study? | 4 | (0) |